This is an HTML version of an attachment to the Official Information request 'Reasons for delay and request for cost for planned install of 12 Watts Design speed humps on Hawkins Hill Road, Brooklyn in March 2024.'.


 
30 April 2024 
 
 
File Ref: IRC-6108  
 
 
 
 
 
Naomi Steenkamp 
[FYI request #25986 email] 
 
 
Tēnā koe Ms Steenkamp 
 
Thank you for your email of 4 March 2024 to Wellington City Council | Te Kaunihera o Pōneke (the 
Council) requesting information regarding speed bumps on Hawkins Hil  Road, Brooklyn. Your request 
has been considered under the Local Government Of icial Information and Meetings Act 1987 
(LGOIMA). Please find my response below.  
 
1.  Please advise the total cost budgeted and approved for the planned install of 12 Watts Design 
speed humps on Hawkins Hil  Road, Brooklyn in March 2024, or as an alternative - please 
provide the cost per hump (i.e. total cost / 12). 
 
I am unable to provide the exact cost for the speed humps (grouped or individual y), nor am I able to 
provide you with the dif erences between the contractor quotations. Where information has been 
provided to the Council by a third party and that information falls in scope of an answer for a LGOIMA 
response, in line with the Ombudsman guidance, the Council consults with the third parties to 
ascertain any concerns that they may have about the information being released.  
 
When consulting with our contractors involved in the project did not want the costs related to specific 
tasks made available, as the information is commercially sensitive. For this reason, I am withholding 
information related to question one pursuant to section 7(2)(b)(ii) of the LGOIMA, to protect 
information where the making available of the information would be likely unreasonably to prejudice 
the commercial position of the person who supplied or who is the subject of the information.  
 
Financial information I am able to provide is the total allocated capital budget of $1,624,000 for the 
minor improvements project to complete works between Ashton Fitchett Drive and the former 
Woffingtons site. To date the Council has spent $1,232,000 on the Hawkins Hil  Right of Way (RoW) 
minor improvements which has been focused between Ashton Fitchett Drive and Southernthread 
Road RoW. The Council has contractual commitments of $196,400 for physical and engineering 
works stil  to be completed between Ashton Fitchett Drive and the former Woffingtons site, bringing 
our actual and committed spend to $1,428,400. 
 
Pending resource consent approval for earth works, the Council wil  be committing the remaining 
$195,600 to carry out sight line visibility improvements and carriage way resealing between 
Southernthread Road RoW and the former Woofingtons before the end of June 2024. Engineering 
works have been undertaken on this section and consideration was given to not completing the earth 
works with the decision made to progress as far as our project budget wil  allow to improve RoW user 
safety on this last section.  
 
2.  Please provide: 
 
a.  the difference in cost between the initial contractor's (Mil s Albert) quotation for the 
works, and the current quotation accepted (PCL Contracting), and; 
 
The tendering process for contractors is completed with an obligation of confidence, as contractors 
provide specific details that relate to their commercial vantage. To maintain the same level of 
 



 
confidence in the Council by current and future contractors, as wel  as the commercial sensitivities 
involved in the contracts themselves, I am withholding the dif erence is cost between contractors 
pursuant to section 7(2)(b)(i ) of the LGOIMA, to protect information where the making available of the 
information would be likely unreasonably to prejudice the commercial position of the person who 
supplied or who is the subject of the information. 
 
b.  the reasons why the "Pavement and Minor Safety Improvement" project only 
commenced 24 February 2022 - some 3 years 3 months after gaining the approval 
and support in the City Strategy Committee Meeting of 22 November 2018 - and is 
stil  not completed 2 years later?  
 
Resolution 4.1.2c of the City Strategy Meeting of 22 November 2018 directed officers to Quantify and 
apply for funding through the 2021 Long-Term Plan (LTP) to deliver improvements and maintenance 
on the RoW which was approved in June 2021. Between July 2021 and February 2022 when the 
project started, Council submitted a request for tender to engage and appoint a contractor to deliver 
the project.  
 
Initially Council had negotiated agreement with private landowners to allow access over private 
property for Hawkins Hil  RoW users so they could exit Long Gully via Wrights Hil  while the RoW was 
closed for maintenance works to occur which was removed in June 2022. This meant our contractors 
could not complete resurfacing works as quickly as expected and a change in methodology was 
needed to complete the works while stil  allowing for traffic movements on the RoW. This change 
combined with increased seasonal rainfall led to our project engineers, Tonkin and Taylor, and 
contractor advising to postpone works until Spring so that they could adjust their methodology and 
wait for better weather to lay asphalt with work recommencing in October 2022.  
 
Except for installing the speed humps, al  work on sections A and B (found in Tonkin and Taylor’s 
Design Report) were completed by March 2023 and by mutual agreement, Mills Albert Contracting 
finished work on the project. Following this, Council investigated options with our roading 
maintenance contractors on how to install the speed humps without closing the road and ended up 
carrying out the works at night which occurred in March 2024.  
 
Council currently has a resource consent underway for earthworks on section C (also found in the 
Tonkin and Taylor Design Report) to improve sightline and visibility and if granted are expecting to 
undertake the work in late May/early June. Upon completion of this stage of work, Hawkins Hill RoW 
wil  revert to our maintenance team in Parks, Sport and Recreation. 
 
As per section 7(1) of the LGOIMA, I do not consider that in the circumstances of this response, the 
withholding of this information is outweighed by the other considerations which render it desirable to 
in the public interest to make the information available.  
 
You have the right, by way of complaint under section 28(1) of the LGOIMA, to request an 
investigation and review of the Council’s decision to withhold information by the Ombudsman. 
Information about how to make a complaint is available at www.ombudsman.parliament.nz or 
freephone 0800 802 602.  
 
If you require further information, please contact [email address]. 
 
 
Nāku noa, nā 
 
 
 
 
Danika Morris-Brown 
Senior Advisor Official Information 
Complaints & Information Assurance 
Wellington City Council